Britton Road
Completed in 2012, this project widened approximately one mile of Britton Road from two lanes to four lanes. As part of a City Bond Issue project, this section of road stretches from County Line Road to Council Road. Johnson & Associates’ responsibilities included grading, drainage (including five concrete box crossings), pavement construction, water line relocation, construction traffic control, ADA sidewalk accessibility, and traffic signal construction. Challenges included, upgrading the roadway typical section from a rural two-lane design to a fully urbanized arterial design with improved & expanded intersection configurations, removal of rural ditches in favor of an underground storm sewer, restrictive Right-of-Way constraints, and phasing the project to work around the relocation of private utilities.