SW 89th & Penn Improvements

This project consisted of widening 1.5 miles of roadway & two miles of roadway overlay, implementing a complete traffic signal replacement at SW 89th Street & S Pennsylvania Avenue (including replacement of interconnect cable), and modifications at SW 89th Street and S Fairview Drive. The project required extensive coordination with utility companies, due to extensive relocation. Storm sewer improvements were designed and constructed to relieve intersection flooding. Storm sewer improvements included extension of 1,000 feet of 48” RCP (despite existing utility conflict design), inlet relocation, and reduction of water trickle flow across commercial sites.